View project: SR 33 (Lakeland Hills Blvd.) from Parkview Place to North of Granada Street
-
This week, crews will continue constructing curb pads and placing curb along side streets, installing light pole bases and conduit for pedestrian signal poles, and completing grading on side streets in preparation for paving & temporary striping.
- Night paving operations are scheduled from May 5 through May 6 on side streets along the east side of Lakeland Hills Boulevard. Work will take place between 7 p.m. and 6:30 a.m. Motorists should expect side street closures and flagging operations. Detours will be in place using adjacent streets, directing traffic toward Gilmore Avenue.
- Ongoing side street work will continue along the east side of Lakeland Hills Boulevard as crews finalize grading and subgrade preparation. Temporary closures may occur, with traffic rerouted via nearby side streets toward Gilmore Avenue.
- Traffic impacts: One lane in each direction will remain open for most of the project duration. Drivers should use caution, be prepared to merge or stop, and allow extra travel time.
- Speed limit: Reduced to 35 MPH within the construction zone.