View project: SR 33 (Lakeland Hills Blvd.) from Parkview Place to North of Granada Street
-
- This week, electrical crews will continue installing signalization, lighting conduit and bases throughout the project. Drainage crews will continue installing drainage along the west side of Lakeland Hills Boulevard. Roadway crews will continue placing limerock base for the new southbound lanes between Crawford Street and Bella Vista Street. Utility crews will continue installing sanitary sewer from Parkview to Channing.
- One lane in each direction will remain open for most of the project duration. Drivers should use caution, be prepared to merge or stop, and allow extra travel time.
- Speed limit: Reduced to 35 MPH within the construction zone.