Project Details
Work Type: Resurfacing
Phase: Construction
Limits: East Gary Road to west of Combee Road
City:
County:
Road:
Construction Cost: $3.7 million
Start of Current Phase: Late 2024
Est. Completion of Current Phase: Mid 2025
About

Project improvements include milling and resurfacing, reconstructing the outside westbound travel lane from Combee Road to North Eastside Drive, removing the traffic separator, adding a keyhole bike lane and upgrading signal equipment at East Lake Paker Drive, drainage improvements, curb, gutter and sidewalk improvements with ADA ramps, driveway reconstruction, and upgrading and adding lighting throughout the project. 

View Factsheet
Contact Information
Communications Team
Sandra Mancil
863-519-4116
Sandra.Mancil@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • Week of Sunday, January 5 through Saturday, January 11, 2025:

    US 92 (East Memorial Boulevard), from Combee Road to North Eastside Drive, will be reduced to one lane westbound when crews will set up a temporary barrier wall on the north side of the road. Taco Bell entrance from US 92 will be temporarily closed. Patrons should enter off Nort Eastside Drive. Use caution and be prepared to merge.