Project Details
Work Type: Resurfacing
Phase: Construction
Limits: East Gary Road to west of Combee Road
City:
County:
Road:
Construction Cost: $3.7 million
Start of Current Phase: Late 2024
Est. Completion of Current Phase: Mid 2025
About

Project improvements include milling and resurfacing, reconstructing the outside westbound travel lane from Combee Road to North Eastside Drive, removing the traffic separator, adding a keyhole bike lane and upgrading signal equipment at East Lake Paker Drive, drainage improvements, curb, gutter and sidewalk improvements with ADA ramps, driveway reconstruction, and upgrading and adding lighting throughout the project. 

View Factsheet
Contact Information
Communications Team
Sandra Mancil
863-519-4116
Sandra.Mancil@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • Week of Sunday, April 13 through Saturday, April 19:

    Expect nighttime/overnight lane closures for milling and resurfacing, Sunday, April 13 through Thursday, April 17. Crews are also expected to remove the barrier wall west of Combee Road on Tuesday night, April 15. Use caution and be prepared to merge.