Project Details
Work Type: Construction Work
Phase: Construction
Limits: US 98 from east of CR 621 to Bridge
Length: 4.7 miles
County:
Road:
Construction Cost: $12.2 million
Start of Current Phase: Late 2023
Est. Completion of Current Phase: Mid 2024
About

The Florida Department of Transportation will begin work on September 16, 2023, to make                  improvements to US 98 from east of CR 621 to the Okeechobee County line in Highlands County. The project limits are approximately 10 miles and the location is shown below.

 

 

The project limits are from West Townsend Street to Batts Street on US 27 and from Self Avenue to US 27 on SR 64 in Highlands County. The project length is approximately half a mile. The project limits are identified below on the project location map.

 

 

PROJECT

 

 

The project limits are from West Townsend Street to Batts Street on US 27 and from Self Avenue to US 27 on SR 64 in Highlands County. The project length is approximately half a mile. 

 

Public Involvement

Nancy Morgan

Community Outreach Manager

Florida Department of Transportation

Heartland Operations Center

(941) 720-6335

nancy.morgan@dot.state.fl.us

 

View Factsheet
Contact Information
Communications Team
Nancy Morgan
941-720-6335
Nancy.morgan@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • US 98 from East of CR 621 to the Okeechobee County Line:  Construction project: Crews will resurface US 98 from east of CR 621 to the Okeechobee County line, reconstruct US 98 in various areas, widen shoulders, replace guardrail, and install signing and pavement markings. During construction there may be daytime and nighttime lane closures and traffic will be reduced to one lane in various areas; temporary signals will be installed to guide motorists. Please use caution in the area and watch for workers in the work zones.

    • Motorists should expect intermittent daytime lane closures between Kissimmee River Bridge and approx. 0.7 miles south of CR 621 to complete paving, striping. Rumble strips, signing and sodding.
    •  Anticipated completion is summer 2024.