EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Milling and Resurfacing
Phase: Construction
Limits: From West of Prescott Road Morgan Grice Road
Length: 3.3 miles
Construction Cost: $5,142,422
Start of Current Phase: Mid 2024
Est. Completion of Current Phase: Early 2025
About

The Florida Department of Transportation will begin work on July 8, 2024, to make  improvements to SR 64 from west of Prescott Road to Morgan Grice Road in Hardee County. The project limits are approximately 3 miles and include milling, resurfacing and other safety improvements.

 

 

 

 

 

Public Involvement

 

Nancy Morgan, Community Outreach Manager

(941) 720-6335

Nancy.morgan@dot.state.fl.us

 

 

FAQs

Project Improvements

  • Resurface SR 64 and road shoulders from westof Prescott Road to Morgan Grice Road
  • Correct roadway cross slopes to current standards which will improve drainage and safety
  • Estimated construction cost is $5 million

Project Schedule

  • Construction begins July 8, 2024;estimated completion is early 2025
  • During construction there may be daytime/nighttime lane closures when traffic will be reduced to one lane with flagging operations
  • While lane closures are in place the speed limit will be reduced to 50 miles per hour
View Factsheet
Contact Information
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
Project Documents