This project has been completed and is only available for historical reference.
Project Details
Work Type: Milling and Resurfacing
Phase: Completed
Limits: SR 70 from Turner Avenue to east of the Ford Dealership in Desoto County
Length: 2.322 miles
Construction Cost: $2.6 million
Completion Date: 09/12/2024
About

The Florida Department of Transportation will begin work in early March to make improvements to SR 70 from Turner Avenue to east of the Ford Dealership in Desoto County. This safety and improvement project will include milling, resurfacing, installing new signal detection loops and pull boxes, signage and pavement markings. The project is approximately 2.32 miles, with limits identified on the map below.

 

Public Involvement

Nancy Morgan, Community Outreach Manager
(941) 720-6335
Nancy.morgan@dot.state.fl.us

 

FAQs

Project Schedule:

  • Construction begins early March, 2024
  • Occasional lane closures on SR 70 are
  • expected and will occur after 8:30 p.m. and before 7:30 a.m.
  • During construction, please use caution in  work zones
  • Estimated completion date is late 2024

Project Improvements

  • Mill and resurface SR 70 from Northeast Turner
  • Avenue to east of the Ford Dealership
  • Install new signage and pavement markers
  • Install new signal detection loops and pull boxes
  • Estimated construction cost is $2.6 million

 

 

 

 

View Factsheet