EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

This project has been completed and is only available for historical reference.
Project Details
Work Type: Resurfacing
Phase: Completed
Limits: south of Coleman Road to CR 542 E (Avenue G NW)
City:
County:
Road:
Construction Cost: $4.5 million
Completion Date: 01/29/2024
About

The Florida Department of Transportation resurfaced Recker Highway from Coleman Road to Avenue G NW in Polk County.  In addition to the improvements listed below, crews added conduit underground just beyond the project limits, from Avenue G NW to CR 542 (K-Ville Avenue). Project improvements included:

  • Mill and resurface the roadway
  • Mill and resurface side street entrances
  • Widen the entrance to Sidney Circle
  • Restripe crosswalks at Avenue G NW, Spirit Lake Road and Coleman Road
  • Upgrade signal equipment
  • Improve Drainage
  • Add additional lighting at intersections
  • Place conduit from SR 542 East to CR 542 West to connect the signals

 

 

View Factsheet
Contact Information
Communications Team
Sandra Mancil
863-519-4116
Sandra.Mancil@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
Project Documents