Project Details
Work Type: Construction Work
Phase: Completed
Limits: from Bell Street to south of Heartland Way
Length: 1 miles
City:
County:
Road:
Construction Cost: $1.3 million
About

Project Description

The Florida Department of Transportation began work on February 7, 2022, to make improvements to US 17 from Bell Street to south of Heartland Way in Hardee County. This project is less than a mile in length.

Project Improvements

  • Repave and widen portions of US 17 from Bell Street to south of Heartland Way
  • Install new signage and pavement markers
  • Improve drainage

 

           

 

Public Involvement

 

 

View Factsheet
Contact Information
Communications Team
Corine Burgess
863-241-1459
Communications Team
Communications Office
FDOT-D1Comm@dot.state.fl.us
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
Project Documents
Project Images
PROJECT LIMITS MAP