Project Details
Work Type: Resurfacing
Phase: Completed
Limits: west of Dude Ranch Road to east of Rattlesnake Road
Length: 1.57 miles
City:
County:
Road:
Construction Cost: $2.8 million
Completion Date: 11/17/2022
About

Construction began Monday, April 11, 2022 on SR 60 from west of Dude Ranch Road to east of Rattlesnake Road and is expected to be completed in late 2022.  Motorists can expect daytime lane closures, primarily between 7 a.m. and 5 p.m., Monday through Friday.  Improvements include:

  • Resurfacing SR 60 and side street entrances
  • Removing acceleration lanes for safety
  • Widening for bike lane striping at the right turn lanes
  • Improving drainage
  • Regrading ditches

 

View Factsheet
Contact Information
Communications Team
Sandra Mancil
863-519-4116
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
Project Documents
Project Images
Preconstruction photo from west of Dude Ranch Road looking east
Preconstruction project from Rattlesnake Road looking west
Preconstruction photo looking east
Project Location Map