441513-1 US 98 north of NW 80th Ave to US 98
Website for Entire Project: http://www.swflroads.com
This project has been completed and is only available for historical reference.
Project Details
Work Type: | Construction Work |
---|---|
Phase: | Completed |
Limits: | US 98 north of NW 80th Avenue to US 98 |
Length: | 6.838 miles |
City: | |
County: | |
Road: | |
Construction Cost: | $8.2 million |
About
The Florida Department of Transportation will begin work on February 14, 2023, to make improvements to US 98 from north of NW 80th Avenue to SR 70 in Okeechobee County. During construction, US 98 will be closed for up to 10 days beginning May 22, 2023. Local traffic will be permitted to access businesses within the project limits.
Public Involvement
David Scarpelli
Community Outreach Manager
Florida Department of Transportation
Heartland Operations Center
(941) 773-7831
View Factsheet
Contact Information
Communications Team |
---|
David Scarpelli
(941) 773-7831
david.scarpelli@qcausa.com
|
For Media Inquiries Only |
fdot-d1comm@dot.state.fl.us
|