Project Details
Work Type: Landscaping Construction
Phase: Completed
Length: 0.186 miles
Construction Cost: $917,500
About

Following the construction of the US 41 and Gulfstream Roundabout in July, Visualscape Inc. began the beautification, irrigation and landscaping of the area. Two staging areas will be used on either side of the roadway.  See attached photo.

To minimize traffic interruptions in the area, lane closures will be limited to overnight hours, starting at 7 p.m. through 6 a.m.  Noise and light from construction vehicles is expected.

The project is expected to take approximately 120 days.