435103-1 Lost Trail over Harney Pond Pedestrian Bridge
This project has been completed and is only available for historical reference.
Project Details
Work Type: | Bridge Construction |
---|---|
Phase: | Completed |
Limits: | Lost Trail over Harney Pond Canal |
Length: | 1 miles |
County: | |
Construction Cost: | $1.6 million |
Completion Date: | 08/31/2022 |
About
Project Description
The Florida Department of Transportation’s contractor began construction of a pedestrian bridge on Lost Trail over Harney Pond Canal in Glades County.
Project Improvements
- Construct a pedestrian bridge on Lost Trail over Harney Pond Canal linking the two sections of the dike
- Install new signage and pavement markers
Public Involvement
View Factsheet
Contact Information
Communications Team |
---|