EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Construction Work
Phase: Construction
Limits: US 41 from Caribbean Drive to SR 72 (Stickney Point Road)
Length: 1 miles
County:
Road:
Construction Cost: $9.9 Million
Est. Completion of Current Phase: Late 2024
About

PROJECT UPDATE:  The Florida Department of Transportation (FDOT) will begin opening the 
remaining medians between Caribbean Drive and Gulf Gate Drive during the month of September. 

Going south on US 41, Bruekner Street will be the only median opening between Gulf Gate Drive and 
Caribbean Drive that will not allow a U-turn  

The Stickney Point Intersection Improvement Project 440685 -1 from Gulf Gate Drive to Stickney Point / SR 72 is expected to be completed in November.  Travel time is currently one to four minutes.

The completion date of these projects was extended due to county utilities delays, material 
acquisition delays, and adverse weather.
 

Public Involvement

Project improvements include: 

· Median modifications to enhance safety

· Drainage improvements

· Construction of improved sidewalks &
a bicycle lane

· Milling, resurfacing, curb and gutter

· New signage and pavement markings

· Intersection Improvements: Stickney Point lighting, signalization and intelligent 
transportation systems.

 

Remaining Project Schedule:  

· Median Openings: September 2024

· Stickney Point Intersection Improvements:
November 2024

· Final Acceptance: November 2024

 

Project Cost: · Estimated at $9.9 million

 

View Factsheet
Contact Information
Communications Team
Barbara Catlin
941-302-5048
For Media Inquiries Only
fdot-d1comm@dot.state.fl.us
RoadWatch
  • US 41 from Caribbean Drive to Stickney Point: Construction: Construction on the next phase along a 1.4-mile area of US 41 from Caribbean Drive to Stickney Point Road is actively underway. Work consists of implementing safety improvements along the corridor including resurfacing, lighting and signalization, median improvements, shoulder reconstruction, improved sidewalks, improved bicycle lanes, as well as needed infrastructure improvements to drainage, curb, and gutter.

    This week, there will be daytime lane closures as they finish out paving and signal work in the area to complete the project.  Please add additional travel time.

    Travel time through the area is only one (1) to five (5) minutes.

Project Documents